The season of the Davis Library.

The season of the Davis Library.

Saturday, August 29, 2015

As August comes to an end...


The progress continues as pictured above in the new main entrance. The white posts will hold a roof for the new entry way and the roof framing is awaiting to the left. The roofs of the additions have been shingled and trimmed. Inside the wiring has been completed and is ready for the new light fixtures and outlets. 

This coming week the windows will be installed!

Monday, August 17, 2015

Last week there was a photo in the Sentinel as the weekly update and since then...


  
         The roofs has been framed and attached.











This is the frame work for the bathroom!










Today plumbers and electricians were in, things are moving swiftly. Stop by and take a look.

Saturday, August 1, 2015

I can see it now...

You can begin to see how it will come together. The windows in additions have been cut. Notice, there will be a large picture window in the children's room, that looks off into the woods, just like the beloved one in the current adult room. When the addition is complete, the new entry way will be the green door facing the parking lot (pictured below).




Next step, the roof!